Second Progress Report

Project Title: Options for FTA Modernisation to Strengthen Critical Mineral Supply Chains for the Indo-Pacific Green Economy Transition

Reporting Period: 7 October 2025 – 6 December 2025

Submitted by: UNSW Centre for Sustainable Development Reform (CSDR) and UNSW Energy Institute


Executive Summary

The project remains on track for completion by 28 February 2026. During this reporting period, we have desk research and iterative informal consultation on industry perspectives, prepared a Consultation Summary, and recalibrated the project approach following discussions with DFAT. Key activities and achievements are summarised below.


Scope Confirmation

All five deliverables from the Grant Agreement remain unchanged and will be delivered as contracted. The project team confirms that any analytical work beyond the originally-agreed scope is undertaken at UNSW's cost and does not impact delivery of contracted deliverables.


Project Team Contributions

Team Member Contributions This Period
Dr. Ben Milligan Project leadership; DFAT liaison and project recalibration discussions; stakeholder consultation design and facilitation; consultation summary development
Professor Iain MacGill Energy markets and policy analysis; review of renewable energy and hydrogen sector perspectives
Dr. Rahman Daiyan Technical input on clean energy supply chains and green hydrogen dimensions
Dr. Michelle Vaqueiro Contreras Analysis of solar and battery manufacturing value chains; regional processing opportunities
Edoardo Santagata Desk research on industry perspectives; evidence synthesis and source documentation

Work Completed This Period

1. Evidence Review Enhancement

Building on the Interim Evidence Review delivered in October 2025, we have continued to refine and expand the analytical foundation:

2. Stakeholder Consultation Activities

Consultation activities during this period have followed the implementation plan outlined in the Inception Report, with adjustments reflecting ongoing consultation with DFAT:

3. Consultation Summary Preparation

The accompanying Consultation Summary synthesises stakeholder perspectives gathered through this period:

4. Project Recalibration

Following discussions with DFAT on 28 November 2025, the project approach has been refined to strengthen alignment with the Southeast Asia FTA Modernisation Review objectives:


Key Findings Preview

Early findings emerging from consultation activities include:

  1. Behind-the-Border Barriers Priority: Stakeholders consistently identify non-tariff measures, regulatory fragmentation, and administrative complexity as more significant impediments than tariff barriers, which are already relatively low under existing FTAs.

  2. Services and Investment Focus: Professional services restrictions, visa and work permit complexity, and investment certainty concerns emerge as cross-cutting priorities affecting multiple sectors.

  3. Standards Harmonisation Opportunity: Strong industry appetite for mutual recognition arrangements covering sustainability standards, professional qualifications, and technical certifications.

  4. Implementation Gap: Existing FTA provisions are often under-utilised due to complexity, awareness gaps, and practical implementation challenges—suggesting that improved utilisation mechanisms may deliver significant value.

  5. Resource Nationalism Management: Industry perspectives on navigating local content requirements and export restrictions while maintaining constructive partnership approaches.


Progress Against Contracted Deliverables

Deliverable Status Progress This Period
Inception Report Complete Delivered October 2025. Established implementation framework and analytical approach.
Evidence Review Published First version delivered October 2025. Continues as a living document with ongoing refinements based on consultation findings.
Consultation Summary Complete First version delivered December 2025. Continues as living document synthesising industry perspectives from consultations and desk research on published stakeholder positions.
Technical Paper In Progress Development to commence January 2026, informed by consultation findings and DFAT guidance on priority areas.
Final Report Planned On track for delivery by 28 February 2026. Will consolidate all project materials with comprehensive FTA modernisation recommendations.

Next Steps

The following activities are planned for the remainder of the project, reflecting the recalibrated approach:

Activity Timeline Notes
Track 2 Virtual Dialogue I 19 December 2025 Industry and regional stakeholder focus
Technical Paper Development January 2026 Incorporating DFAT guidance on priorities
Government Agency Engagement January–February 2026 After industry input crystallised
Track 2 Virtual Dialogue II February 2026 Final recommendations validation
Final Report Delivery 28 February 2026 Comprehensive FTA modernisation recommendations

Risks and Mitigations

Risk Likelihood Impact Mitigation
Stakeholder availability during holiday period High Medium The December–January period presents inherent challenges for industry consultation, with reduced stakeholder availability during the Australian summer holiday season and competing year-end business priorities. Consultation activities continue through this period where possible, with the consultation program designed to accommodate variable response rates. Should engagement prove lower than anticipated during December and January, the project retains flexibility to expand the scope of consultation activities and roundtables in February 2026, prior to final report delivery.
Scope alignment with DFAT priorities Low High The 28 November 2025 discussions with DFAT have clarified priority areas and consultation sequencing. Ongoing communication with DFAT will ensure continued alignment as recommendations develop.

The project team is actively monitoring stakeholder engagement levels and will adapt the consultation program as needed to ensure robust industry input informs the final recommendations.


Budget Status

Expenditure during this period has been in line with budget projections. The project team has utilised UNSW in-kind contributions for research personnel and facilities as outlined in the grant agreement. No budget variations are anticipated.


Conclusion

The project is progressing on schedule with stakeholder engagement and emerging consensus on priority themes for FTA modernisation. Following discussions with DFAT, the project approach has been recalibrated to prioritise industry consultation and focus on behind-the-border barriers—reflecting the most significant implementation challenges identified by stakeholders. The Consultation Summary accompanying this report documents stakeholder perspectives that will inform the Technical Paper and Final Recommendations.


Authorised by:

[Signature]

Dr. Ben Milligan Scientia Fellow and Director UNSW Centre for Sustainable Development Reform

Date: 6 December 2025